Regulators deny quick approval of new Great Lakes pipeline

In this June 8, 2017, file photo, fresh nuts, bolts and fittings are ready to be added to the east leg of the Enbridge Line 5 pipeline near St. Ignace, Mich., as Enbridge prepares to test the east and west sides of the Line 5 pipeline under the Straits of Mackinac in Mackinaw City, Mich. Photo: Dale G. Young/Detroit News via AP, File. In this June 8, 2017, file photo, fresh nuts, bolts and fittings are ready to be added to the east leg of the Enbridge Line 5 pipeline near St. Ignace, Mich., as Enbridge prepares to test the east and west sides of the Line 5 pipeline under the Straits of Mackinac in Mackinaw City, Mich.

Associated Press
Created: June 30, 2020 02:23 PM

A Michigan regulatory panel on Tuesday refused to grant quick permission to run a new oil pipeline beneath a channel that connects two of the Great Lakes, deciding instead to conduct a full review.

Enbridge filed an application in April with the Michigan Public Service Commission to relocate a segment of its Line 5 that extends beneath the Straits of Mackinac, which links Lakes Huron and Michigan.

Advertisement

The Canadian energy transport company wants to replace dual pipelines that rest on the lake floor with a new pipe that would be placed in a 4-mile-long (6.4-kilometer-long) tunnel to be drilled in bedrock beneath the waterway.

Enbridge asked the state commission to approve the plan immediately, arguing that the agency in effect had already given permission by allowing the original Line 5 in 1953. But during an online meeting Tuesday, the panel disagreed on a 3-0 vote.

Members concluded that the proposed tunnel pipe "differs substantially" from the twin pipes that were laid 67 years ago, requiring a new easement and a 99-year lease of public trust property.

The project "involves important factual, policy and legal issues best resolved through a proceeding that includes discovery, comprehensive testimony and evidence to provide a robust record," the commission said in a statement. It scheduled a public hearing for Aug. 24.

Enbridge's argument that the commission didn't need to conduct an extensive study of the plan drew opposition from Michigan Attorney Dana Nessel and numerous members of the public who submitted written comments and spoke during the online meeting.

"Enbridge has already shown that they cannot be trusted," said Sean McBrearty of the environmental coalition Oil & Water Don't Mix. The public service commission, he said, "must thoroughly study this proposal and its potential impacts on our water and climate before making their final ruling."

Enbridge spokesman Ryan Duffy said Enbridge "respects the Michigan Public Service Commission's decision and we look forward to the next steps in the regulatory process."

The commission made its decision as Nessel's office and Enbridge prepared to face off in a state courtroom over a judge's temporary order last week to shut down the existing Line 5 pipes because of recently discovered damage to a support anchor.

Circuit Judge James Jamo was scheduled to hear arguments Tuesday on whether to extend the order or allow oil to resume flowing through the pipes.

Line 5 carries about 23 million gallons (87 million liters) of crude oil and natural gas liquids used in propane between Superior, Wisconsin, and Sarnia, Ontario, spanning portions of Michigan's upper and lower peninsulas.


(Copyright 2020 by The Associated Press. All Rights Reserved.)

Comment on Facebook
Advertisement

5 INVESTIGATES: Juul recruited U of M researcher as vaping controversy intensified

Private schools, law firms among biggest PPP loan recipients in Minnesota

Police: 12-year-old shot in Minneapolis following road rage incident

Warm weather, scattered storms expected Tuesday

Twins open season July 24 at White Sox, feature 7 home games vs. Indians

New rules: Foreign pupils must leave US if classes go online

Advertisement